IF ARBITRATION IS TO SUCCEED , EVEN ARBITRATORS NEED TO BE PROTECTED AGAINST SUCH ACTS OF BROWBEATING
http://lobis.nic.in/ddir/dhc/NAC/judgement/17-08-2018/NAC14082018OMPTCOMM452018.pdf
WORLDS WINDOW INFRASTRUCTURE & LOGISTICS PVT. LTD.
Vs.
CENTRAL WAREHOUSING CORPORATION
ARB.P. 437/2018 & IA No. 7725/2018
+ O.M.P. (T) (COMM.) 45/2018 & IA No. 7727/2018 DECIDED ON 14-8-2018
Read More
ARBITRATOR IS BOUND BY THE FEE SCHEDULE AGREED BY THE PARTIES IN THE AGREEMENT
http://lobis.nic.in/ddir/dhc/NAC/judgement/28-07-2018/NAC20072018OMPTCOMM392018.pdf
NATIONAL HIGHWAYS AUTHORITY OF INDIA
Vs.
GAMMON ENGINEERS AND CONTRACTOR PVT LTD
POST AWARD INTEREST AS PER BANK CERTIFICATE IS 16.20% AS PER 31(7)(b) OF THE ARBITRATION AND CONCILIATION ACT
http://lobis.nic.in/ddir/dhc/NAC/judgement/21-08-2018/NAC16082018OMPENFCOMM552017.pdf
M/S ARSS INFRASTRUCTURE PROJECTS LTD
Vs.
CALCUTTA HALDIA PORT ROAD COMPANY LTD