PAYMENT FOR EXTRA WORK:
ICON-5 PAYMENT FOR EXTRA WORK: Contractor informed that he is doing some extra work as per site requirement- XEN requested not to do but till that time extra work had already been done-Claim justified.
Read MoreDEMAND OF MARKET RATES
ICON-4 Demand of market rates: If the department didn’t refute the analysis of rates at the time of submission by the agency- It would be deemed as accepted.
Read MoreANALYSIS OF CLAUSE 12 CPWD CONTRACTS
Clause 12: This clause deals with following situations: This clause gives following powers to Engineer-in-Charge for which the contractor shall be bound to carry out the works:- to make alteration in to make omissions from to make additions to or substitutions for the original specifications, drawings, designs and instructions that may appear to him to be necessary or advisable during the progress of the work and also to omit a part of the works